US Court Stays Ruling Against Dominion Atlantic Coast Pipeline
1/31/2019
Reuters – A U.S. appeals court has stayed a previous court decision against Forest Service permits that allowed Dominion Energy to build the $7 billion Atlantic Coast natural gas pipeline across national forests and the Appalachian Trail.
The 4th Circuit Court of Appeals on Tuesday froze the previous decision by a three-judge panel until the full court decides whether it will rehear the case en banc.
The appeals court panel had said in December that the U.S. Forest Service had “abdicated its responsibility to preserve national forest resources” when it issued the permits.
Dominion argued that the ruling by the three-judge panel to vacate the Forest Service permits went beyond the court’s authority and created an “impregnable barrier (from Georgia to Maine) dividing energy sources west of the (Appalachian) Trail from consumers east of the Trail.”
Dominion spokesman Karl Neddenien said the company remained confident it would complete the 600-mile (966-km) pipeline from West Virginia to North Carolina, even though the timing is “somewhat fluid” due in part to federal lawsuits.
In the past, Dominion said it expected to finish the project in mid-2020, but the company has suspended all construction since early December after the 4th Circuit stayed a federal permit in another lawsuit.
Related News
Related News
Sign up to Receive Our Newsletter
- Keystone Oil Pipeline Resumes Operations After Temporary Shutdown
- Biden Administration Buys Oil for Emergency Reserve Above Target Price
- Freeport LNG Plant Runs Near Zero Consumption for Fifth Day
- Enbridge to Invest $500 Million in Pipeline Assets, Including Expansion of 850-Mile Gray Oak Pipeline
- Williams Delays Louisiana Pipeline Project Amid Dispute with Competitor Energy Transfer
- Evacuation Technologies to Reduce Methane Releases During Pigging
- Editor’s Notebook: Nord Stream’s $20 Billion Question
- Enbridge Receives Approval to Begin Service on Louisiana Venice Gas Pipeline Project
- Russian LNG Unfazed By U.S. Sanctions
- Biden Administration Buys Oil for Emergency Reserve Above Target Price
Pipeline Project Spotlight
Owner:
East African Crude Oil Pipeline Company
Project:
East African Crude Oil Pipeline (EACOP)
Type:
TotalEnergies in discussions with a Chinese company after Russian supplier Chelpipe was hit by sanctions.
Length:
902 miles (1,443 km)
Capacity:
200,000 b/d
Start:
2022
Completion:
2025