(Reuters) — Canada's Enbridge Inc. said on Thursday it was "disappointed" by the U.S. Army Corps of Engineers' decision to extend the federal permitting process for the company's proposed Great Lakes Tunnel that would rehouse its Line 5 oil pipeline underneath the Straits of Mackinac.
Calgary-based Enbridge said the move will delay its plan to replace a section of the existing Line 5 pipeline, which runs underwater for four miles (6.4 km) between Lakes Michigan and Huron and push back the start of construction until 2026.
"While we are supportive of a thorough, comprehensive and carefully considered permitting process that ensures adequate opportunity for review and comment, we are disappointed with the extended timeline for a project of this scope," Enbridge spokesman Ryan Duffy said in a statement.
Enbridge submitted an application to build the $750 million tunnel in 2020 to address concerns Line 5 could leak into the Great Lakes. The 70-year-old pipeline carries 540,000 barrels per day from Superior, Wisconsin, to Sarnia, Ontario, and is at the center of a long-running legal dispute between Enbridge and the State of Michigan, which says it should be shut down.
The Detroit District of the U.S. Army Corps of Engineers (USACE) is responsible for evaluating Enbridge's permit application and received more than 17,000 public comments during a scoping period that ended in October 2022, the USACE said in a statement.
The regulator had originally planned to publish a draft environmental impact statement on the Line 5 tunnel project in late 2023, but has pushed that back to spring 2025.
"We greatly appreciate the meaningful input received throughout scoping and will use this information to shape studies and continuing consultations throughout development of our draft environmental impact statement," said Detroit District Commander Lieutenant Colonel Brett Boyle in a statement.
Related News
Related News

- PG&E Reduces Emissions from Gas Pipelines by More Than 20%
- Trans Mountain Pipeline Expansion Project to Nearly Triple Current Capacity to 890,000 bpd
- Spain's Tecnicas Reunidas, FCC to Build LNG Terminal Worth $1.1 Billion in Germany
- Canada Offers $26 Billion Green Tax Credits But Still Trails Behind US Incentives
- Pipeline Operator TC Energy Says Keystone Oil Spill Caused by Fatigue Crack
- Pipeline Operator TC Energy Says Keystone Oil Spill Caused by Fatigue Crack
- Permian In Spotlight as Energy Dealmaking Gathers Steam
- Trans Mountain Pipeline Expansion Project to Nearly Triple Current Capacity to 890,000 bpd
- Colombia's Cano Limon-Covenas Pipeline Attacked for Ninth Time in 2023
- Chad Nationalizes Exxon’s 621-Mile Pipeline as Dispute Over Asset Sale Escalates
Comments